Flow Chart of Services for Residential Building
- Owner delivers plans to Permit Office and pays for Plan Review
- Plans delivered or picked up by Building Inspection Group for review (allow 10 days)
- Plans returned to Permit Office with Letter of Approval or Corrections
- Permit issued or denied / Owner pays for permit
- Each Craft or Trade group supervisor calls Building Inspection Group dispatch office for each inspection when ready (allow 24 hours (max) for scheduling)
- Upon completion of all final inspections a letter of completion is delivered to Permit Office
- Certificate of Occupancy is issued by the Permit Office
NOTE: Any inspection not performed due to inaccessibility of premises or premature call out will be subject to additional inspection fees.